Time Loads for Construction Stage

 

 

Impose Time Load to specific members to reflect the time dependent material properties relative to the contiguous members.

 

 

 

From the Main Menu select Load > Construction Stage> Construction Stage Loads > Time Loads for Construction Stage.

 

 

 

Load Group Name

Select a Load Group in which the Time Load is to be included.

 

Options

Add: add a time load to the selected members.

Replace: change the time loads assigned to the selected members.

Delete: delete the time loads assigned to the selected members

 

Time Loads

Loads pertaining to simple passage of time to reflect the change of time dependent material properties